Seventy years of Kenny, twenty-five years of shrinking enrollment, a citywide redesign, and a transformation process building since 2023.

Jump to:
  1. 1948Kenny
    Park Board acquires the land for Kenny Park

    The Minneapolis Park Board acquires the site, a former gravel pit. It was planned as a shared campus between the park board and the school board.

  2. 1954Kenny
    Kenny Elementary is built

    Kenny is built as a community school in postwar Southwest Minneapolis. MPS lists the building at 60,104 square feet, designed for about 389 students.

  3. Oct 1955Kenny
    Kenny Park dedicated

    The park is named for Sister Elizabeth Kenny, the polio nurse behind Minneapolis's Sister Kenny Institute. It sits between Kenny Elementary and Anthony Middle School (opened 1958) on a campus designed for shared use.

  4. 2001-02District
    MPS enrollment peaks

    District enrollment peaks at roughly 46,000 students. It has declined through most of the years since.

  5. 2005-2010District
    The last major round of closures

    MPS closes more than a dozen schools, concentrated in North Minneapolis. Tuttle closes in 2007 and is still district-owned and pending sale in 2026. No Southwest school, Kenny included, appears on those closure lists.

  6. Nov 4, 2008Board decision
    Voters restructure the board, after the board said no

    The legislature had given the school board a choice in 2006: vote to switch from seven at-large seats to six district seats plus three at-large, or put it to voters. The board voted against the change itself. Voters then approved it directly, about 66% (104,283-54,042) — the same structure the board still uses today. A similar proposal had failed once before, in 1987.

  7. Nov 30, 2011Money
    $45 million to reopen what the district had just closed

    The board approves a $45 million plan to reopen three closed schools (Howe, shut in 2005; Folwell, shut in 2010) and move more than 4,000 students, after enrollment rose 330 students that fall — the district's first increase in a decade. Howe and Folwell reopen in 2012-13; the district had been trying to sell the Howe building. This is the same institution now proposing to close up to 16 more schools.

  8. Jul 1, 2016District
    Ed Graff named superintendent — the district's third permanent leader since 2006

    Graff, previously superintendent in Anchorage, is appointed after the board's first choice, Sergio Paez, fell through: two days after selecting him in Jan 2016, the board learned of a criminal investigation into alleged abuse of special education students by staff under him, and ended negotiations.

  9. 2017Kenny
    Kenny building rated in "poor condition"

    A districtwide facilities assessment rates Kenny's building in poor condition. MPS said a new assessment would happen in 2025; as of Sept 15, 2026 no result is posted.

  10. 2018-19Kenny
    Kenny enrollment near its high point

    Kenny enrolls roughly 470-480 students, more than its design capacity (federal data as compiled by third-party sites; year labels vary by source).

  11. May 12, 2020Board decision
    Board approves the Comprehensive District Design (CDD)

    The board votes 6-3 to redraw attendance boundaries for nearly every school, centralize magnet schools and cut K-8s from eight to two. The plan explicitly avoided closing schools. It took effect in fall 2021.

  12. Fall 2021District
    New boundaries take effect; enrollment falls

    The city auditor estimates the redesign contributed to 4,200+ students leaving MPS within two years. Kenny's enrollment falls from roughly 410 to roughly 330 around this period.

  13. Mar 2022District
    First Minneapolis teachers' strike in 50 years ends

    The roughly three-week strike ends with raises, class-size caps and a social worker in every building.

  14. Jun 30, 2022District
    Graff departs after the teachers' strike; Cox named interim

    Graff announces he will not continue weeks after the March 2022 strike. Rochelle Cox, a 25-year MPS veteran, is named interim superintendent unanimously.

  15. Jan 10, 2023Board decision
    Last full CDD progress report to the board

    The district reports that the number of elementary schools under its 300-student programming threshold went up by one after the redesign. The Star Tribune later reports no CDD progress report had been given since early 2023.

  16. Dec 2023Board decision
    Board launches "School Transformation"

    After a first reading on Nov 14, 2023, the board adopts Resolution 2023-0072, starting a process that includes closing and consolidating schools among the options to study.

  17. Feb 5, 2024District
    Dr. Lisa Sayles-Adams starts as superintendent

    Selected by the board 8-1 on Dec 1, 2023, the same month the board adopted the transformation resolution. She is the district's fourth permanent superintendent since 2016.

  18. Oct 2024Kenny
    Physical space study walks every building

    Board members, principals, teachers and staff walk through all MPS buildings. Kenny is recorded at 295 students, about 76% of design enrollment, which the district's own report calls "efficient." The study, released in November, finds about half of buildings underused. The Southwest schools named as underused were Burroughs and both Lake Harriet campuses, not Kenny.

  19. Oct 14, 2025Board decision
    Resolution 2025-0045 adopted 7-1

    The board directs the superintendent to report on closing, consolidating and repurposing schools, including a cost/benefit analysis for any physical change. An amendment to define the undefined target "sweet spot" as 70-89% capacity fails 2-6.

  20. Apr 7, 2026Board decision
    Five "parameters" introduced

    Staff present five parameters that will drive options: enrollment targets, minimum program size, program types, building utilization (example target 80-90%) and community school boundaries.

  21. Apr 21, 2026Kenny
    School-size table presented

    A slide on K-8 schools says the K-5 portion needs 485-795 students at schools like Kenny (under 70% free/reduced lunch) to deliver the full "MPS student experience." Kenny's building holds about 389 at full design capacity.

  22. May 2026Money
    Six empty buildings, and selling them won't close the gap

    The Star Tribune reports MPS holds six vacant buildings. District operations chief Tom Parent says an empty elementary costs $50,000-$80,000 a year to maintain and a sale can take two years or more.

  23. May 19, 2026Board decision
    Timeline set: options in September, decisions in November

    Staff lay out the calendar. Decisions made after Nov 10, 2026 would likely push any changes to the 2028-29 school year.

  24. Jun 9, 2026Money
    $1 billion budget adopted with a deficit

    The board adopts the 2026-27 budget with a shortfall of roughly $37-40 million (reported figures vary) and directs the superintendent to bring back options this fall.

  25. Aug 11, 2026Board decision
    Board Chair Beachy finishes second in his own primary

    In the citywide at-large primary, Christin Crabtree leads with 49,254 votes to Chair Collin Beachy's 43,276. Both advance to the Nov 3 general — seven days before the Nov 10 vote on school closures.

  26. Aug 26, 2026Kenny
    Kenny named a 2026 Minnesota School of Excellence

    The Minnesota Elementary School Principals' Association recognizes Kenny after a self-study and peer review process aligned with national standards for leadership, learning and community engagement.

  27. Aug 26, 2026Money
    Another accounting error: $4.1 million lost

    The Minnesota Reformer reports MPS lost $4.1 million in special education aid by under-reporting expenses, alongside other financial errors and adverse audit findings.

  28. Sep 15, 2026Board decision
    Callahan: "We did not ask for a list of schools to close"

    At the same meeting the three options are unveiled, Director Callahan reads a statement saying the board directed staff to deliver three transformation options, not a closure list, and that a small group of staff drew the plan up "behind closed doors." Director Emerick calls the process "very courageous." Chair Beachy asks staff directly how much of the district's structural deficit the plan actually solves; the deputy superintendent answers that closures are not "a huge cost savings."

  29. Sep 15, 2026Board decision
    Kenny named for closure in all three options

    At a 5:00 PM board work session the superintendent presented three transformation options. Kenny appears only on the "current" side of the Southwest Pathway diagrams (slides 71-73) and is listed by name as an unprogrammed building on slide 82 in Option 1, Option 2 and Option 3. The same deck codes Kenny orange, "large enough for MPS student experience." Informational item, no vote.

  30. Sep 15, 2026Board decision
    Board hears the options: no savings figure, no size number, no question about Kenny

    In 92 minutes of questions after the presentation, the deputy superintendent told the board closures are "not something that's like a huge cost savings"; Director Norvell asked for the "optimal size" number and got no answer; Director Callahan called the options "offensive" and asked for per-school savings by Oct 13; three members said the timeline is too short. No board member asked about Kenny. No vote.

  31. Sep 16, 2026District
    Staff meetings begin at the schools on the list; survey opens

    District staff meet with staff at each school proposed to close or merge, starting 8:15 AM. Principals were called before the Sept 15 meeting. The online survey and interactive map open the same day and run through Oct 16.

  32. September 16, 2026Kenny
    Kenny parent interviewed on WCCO Radio

    Rob Thesing appeared on The WCCO Morning News with Vineeta Sawkar the morning after the board heard the three options, raising the district's missing progress report on the 2020 Comprehensive District Design and the absence of any published savings figure for the proposed closures.

  33. Today
    Oct 13, 2026Board decisionUpcoming
    Business meeting: public comment, and Callahan's three questions due

    Director Callahan asked the district to answer by this meeting: per-school savings, the share of displaced students expected to stay in MPS, and what each listed school needs to stay open.

  34. Oct 20, 2026Board decisionUpcoming
    Work session: initial community feedback reported

    The district calls it a checkpoint. It will report who it heard from, then refine the plan before any November decision.

  35. Nov 3, 2026Board decisionUpcoming
    General election decides 5 of 9 seats — one week before the vote

    Five of the nine board seats are decided at the polls, including the chair's, seven days before the board votes on closures. Three of the nine members casting that Nov 10 vote — Skjefte, Norvell, Emerick — are not on this ballot and leave office in January 2027. Skjefte was appointed in 2024 and has never faced a voter.

  36. By Nov 10, 2026Board decisionUpcoming
    Practical deadline for 2027-28 changes

    District staff say decisions after this date would likely push implementation to 2028-29.

  37. Fall 2027Board decisionUpcoming
    Target start for any changes

    The district's stated goal for implementing program and site changes.

Know someone who's lived through this history?
Keep Kenny

An independent community site about Minneapolis Public Schools' "School Transformation" process and Kenny Community School. Not affiliated with Minneapolis Public Schools, Kenny Elementary or the Kenny Parent Foundation.

Our standard

Facts link to their source. Our argument is labeled as argument. Where sources disagree, we show the range. Spot an error? Tell us and we will correct it publicly.